Title
Staff Report for a City of San Leandro City Council Resolution to Accept the Work for the Annual Street Sealing 2019-2020 - Curb Ramp Upgrade Phase Project, Project No. 2020.0070
Staffreport
SUMMARY AND RECOMMENDATIONS
This construction contract installed new concrete curb ramps and upgraded existing curb ramps to current Americans with Disabilities Act (ADA) standards at thirty-four (34) locations in the City as part of the Annual Street Sealing 2019-2020 Project.
Staff recommends the following actions:
• Accept the work by FBD Vanguard Construction, Inc.;
• Authorize the City Manager to file the Notice of Completion;
• Authorize the City Manager to release the performance and payment bonds; and
• Authorize the City Manager to Release the maintenance bond upon successful completion of the one-year maintenance period.
BACKGROUND
The ADA mandates construction of curb ramps at street intersections when roadway pavement is replaced, overlaid, or treated with cape seal. This contract installed ramps at locations where pavement work is planned as part of the Annual Street Sealing 2019-2020 project. The Street Sealing work needs to occur during warm months and because of delays due to COVID-19 Health Orders, construction was postponed until the summer of 2021. Curb Ramp construction was delayed but not postponed. Three (3) new ramps were installed at locations where none existed, and thirty (30) existing non-compliant ramps were upgraded.
Curb ramps are a vital component of the pedestrian path of travel and an important element in implementing the City’s Complete Streets policy. Ramps allow persons with mobility disabilities to safely cross streets, and they make the City’s sidewalks accessible, regardless of physical ability. Each ramp includes a panel of raised tactile domes to warn the vision impaired of a street crossing.
Analysis
Construction is complete. The work was inspected and found in compliance with the contract documents and City standards.
The Contractor was unable to achieve the stated goals of the Community Workforce Agreement (CWA). The contractor requested workers from local Union Halls but with sparse results, attracting 1% of the workforce from San Leandro and 29% from within Alameda County. The contractor could not meet the CWA goals; however, the contractor supported its effort with documented good faith efforts that were in compliance with the City’s ordinance.
Current Agency Policies
• Maintain and enhance San Leandro’s infrastructure
Previous Actions
• On May 6, 2020, by Resolution No. 2020-061, the City Council awarded a contract for the construction of the Annual Street Sealing 2019-2020 - Curb Ramp Upgrade Phase Project to FBD Vanguard Construction, Inc.
Applicable General Plan Policies
• Transportation Goal T-2 Design and operate streets to be safe, attractive, and accessible for all transportation users whether they are pedestrians, bicyclists, transit riders or motorists, regardless of age or ability.
• Transportation Goal T-3 Promote and accommodate alternative, environmentally-friendly methods of transportation, such as walking and bicycling.
• Transportation Goal T-5 Improve major transportation arteries for circulation in and around the City.
Environmental Review
This project is categorically exempt from CEQA review per CEQA Guidelines section 15301(c). The Notice of Exemption was filed with the Alameda County Recorder on February 7, 2020.
Summary of Public Outreach Efforts
• The Notice to Bidders was published in the Daily Review, the South County Post, Vision Hispana and Sing Tao.
• Notices were issued to twenty-three builders’ exchanges and construction data firms as well as a list of contractors that have asked to be notified of bidding opportunities via email.
• The project was described on the Engineering and Transportation Department website.
Fiscal Impacts
The total project cost of $2,500,000 includes the deferred Street Sealing phase and is as follows:
Design and Bid: $30,000
Construction Contract: $339,588
Contract Change Order: ($18,555)
Construction Management and Inspection: $24,000
Sub-total for the Curb Ramp Upgrade Phase: $375,033
Street Sealing (Deferred to 2021) $2,124,967
Project Total $2,500,000
Change Order Summary
Change Order limit authorized at contract Award: $84,895 (25%)
CCO No. Description Amount %
1.0 City added scope to address conforms at private
property unforeseen at the time of bid $7,165 2%
2.0 City added bulb-out to address underground
Utility obstructions unforeseen at the time of bid $16,122 5%
3.0 Increases and decreases in quantities; actual
measured quantities differed from quantities
estimated at bidding, no change in scope $(41,842) (12)%
Change Order Total $(18,555) (5)%
Budget Authority
Account No. Source FY/Approp Date. Amount
144-38-412 Measure B Streets FY19-20 $1,500,000
143-38-412 Vehicle Registration Fees FY19-20 $400,000
210-38-412 General Fund FY19-20 $600,000
Total Project Appropriation: $2,500,000
Attachment to Staff Report
• Annual Street Sealing 2019-2020 - Curb Ramp Upgrade Phase Project Photos
PREPARED BY: John O’Driscoll, Associate Engineer, Engineering and Transportation Department