File #: 24-363    Version: 1 Name: SR for WPCP CIP Plan and Appropriation
Type: Staff Report Status: Agenda Ready
In control: Finance Committee
Meeting Date: 9/25/2024 Final action:
Enactment date: Enactment #:
Title: Staff Report on Water Pollution Control Plant 10-Year Capital Improvement Program (CIP) Plan and Fiscal Year 2024-25 Appropriation of $2,660,000 from the Water Pollution Control Fund
Sponsors: T. Michael Yuen
Attachments: 1. CIP Plan Overview for Finance Committee.pdf, 2. Attachment A: Resolution to Appropriate $2,660,000 from the Water Pollution Control Fund Balance for Fiscal Year 2024-25 Capital Improvement Needs, 3. Attachment B: Draft 2024-25 Water Pollution Control Capital Improvement Plan

Title

Staff Report on Water Pollution Control Plant 10-Year Capital Improvement Program (CIP) Plan and Fiscal Year 2024-25 Appropriation of $2,660,000 from the Water Pollution Control Fund

 

Staffreport

COUNCIL PRIORITY

                     Infrastructure

                     Sustainability & Resiliency

 

SUMMARY

 

Review the 2025 to 2034 Capital Improvement Program (CIP) Plan and appropriate $2,660,000 from the Water Pollution Control Fund to fund the 2024-25 CIP projects.

 

RECOMMENDATIONS

 

Staff recommends the City Council Finance Committee review the Water Pollution Control CIP Plan and recommend to City Council an additional 2024-25 appropriation of $2,660,000 from the Water Pollution Control Fund.

 

BACKGROUND

 

The City’s Water Pollution Control Plant (WPCP) processes wastewater for the northern two-thirds of San Leandro. The wastewater is collected via a network of 125 miles of sewer pipes and 12 lift stations. The WPCP process about 5 million gallons of wastewater per day. The WPCP was originally constructed in the 1930s and has been upgraded multiple times since then, most recently in the 2015 rehabilitation project.

 

WPCP operations and capital needs are funded through sewer fees. As required by Proposition 218, sewer fees are kept in the Water Pollution Control enterprise fund and are only used for that purpose.

 

To properly maintain critical infrastructure like the WPCP and sewer collection system, it is necessary to periodically review the status of that infrastructure and plan for potential capital outlays that will enable it to continue to provide consistent and reliable service. This plan should identify needs for renewal as well as ways to extend the useful life of the current facilities. In addition, changes in regulation and climate change also require advance planning.

 

City staff worked with Jason Warner, a wastewater engineer with extensive experience with treatment plants, to create a plan that has three main goals: respond to changing regulations; maintain a high-functioning and reliable facility; and set a basis for ongoing cash flow management and an upcoming sewer rate study.

 

The staff report is intended to provide an overview of the WPCP’s Capital Improvement Program Plan for informational purposes. Staff is also proposing an appropriation for fiscal year 2024-25 to fund the current year projects. The plan was not yet complete for the mid-cycle budget requests and several urgent items have been included for the first year of the plan. Funding for future years will be included with the budget process.

 

Analysis

 

The WPCP’s CIP was developed with three overarching goals:

 

1.                     Respond to changing regulations.

In July 2024, the San Francisco Bay Regional Water Quality Control Board (“Water Board”) imposed limits for the first time on the quantity of nitrogen that can be discharged to San Francisco Bay. Complying with this requirement will require changes to the WPCP. The plan sets forth a strategy for identifying cost-effective changes while maintaining flexibility to meet lower limits if necessary.

2.                     Maintain a high-functioning, reliable facility.

The WPCP and the collection system have a strong history of permit compliance. To continue this, the plan identifies areas of the plant and collection system that will need upgrades or replacement in the next 10 years. In addition, it recommends measures to extend the life of the current assets. By carefully managing the City’s assets, the plan seeks to provide the greatest value over the long term.

3.                     Set a basis for ongoing cash flow management and an upcoming sewer rate study.


Proposition 218 requires that sewer rates be justified by expenses incurred in the collection and processing of wastewater, including capital expenses and reserve requirements. The City has entered into an agreement with a consultant to analyze the sewer rates and propose any necessary sewer rate increases. Proposed rates will be brought before the Finance Committee in Spring 2025.

 

Applicable General Plan Policies

 

                     Policy EH-1.8 Sea Level Rise. Consider the effects of projected sea level rise in the design and planning of all development, recreational improvements, and infrastructure along the San Leandro shoreline.

                     Action EH-1.8. A: Adaptation Plans. Develop long-term adaptation plans which minimize the potential for coastal flooding on public and private properties near the San Leandro shoreline. Periodically evaluate the risk to homes, businesses, parks, and other features and take steps to protect or fortify these areas to reduce damage potential.

                     Policy CSF-6.4 Wastewater Collection and Treatment. Maintain efficient, environmentally sound, and cost-effective wastewater collection and treatment services in San Leandro.

 

Financial Impacts

 

Staff requests the Finance Committee forward to City Council the recommendation to appropriate $2,660,000 from the Water Pollution Control Undesignated Fund Balance into Account 593-52 for the WPCP’s Fiscal Year 2024-2025 CIP. This recommendation will draw down the Water Pollution Control Fund’s undesignated fund balance and has no General Fund impact.  

 

ATTACHMENTS

Attachment A: Resolution to Appropriate $2,660,000 from the Water Pollution Control Fund Balance for Fiscal Year 2024-25 Capital Improvement Needs

Attachment B: Draft 2024-25 Water Pollution Control Capital Improvement Plan

 

 

PREPARED BY:

Hayes Morehouse

Water Pollution Control Manager

City Manager’s Office