Skip to main content
File #: 23-320    Version: 1 Name: Amendment No. 7 to NPSA for Turf Maintenance with Rubicon Landscape
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 7/10/2023 Final action: 7/10/2023
Enactment date: Enactment #: 2023-096
Title: Adopt a Resolution to Approve and Authorize the City Manager to Execute Amendment No. 7 to a Non-Professional Services Agreement with Rubicon Landscape Corporation for Citywide Turf Maintenance for $111,018.88 from July 1, 2023 to January 31, 2024
Attachments: 1. A - Resolution For Rubicon Amendment No. 7, 2. B - Exhibit B Compensation Schedule 2023-2024, 3. C1 - NPSA Rubicon 2016, 4. C2 - Amendment No. 1 Rubicon 2017, 5. C3 - Amendment No. 2 Rubicon 2018, 6. C4 - Amendment No. 3 Rubicon 2019, 7. C5 - Amendment No. 4 Rubicon 2020, 8. C6 - Amendment No. 5 Rubicon 2021, 9. C7 - Amendment No. 6 Rubicon 2022

Title

Adopt a Resolution to Approve and Authorize the City Manager to Execute Amendment No. 7 to a Non-Professional Services Agreement with Rubicon Landscape Corporation for Citywide Turf Maintenance for $111,018.88 from July 1, 2023 to January 31, 2024

 

Staffreport

COUNCIL PRIORITY

                     

                     Infrastructure

 

SUMMARY

 

The City has a Non-Professional Service Agreement with Rubicon Landscape Corporation to provide turf maintenance services at City parks and sports fields. The proposed amendment for a contract extension will provide additional time for staff to issue a comprehensive RFP for services with a new contract start date no later than February 1, 2024.

 

RECOMMENDATION

 

Staff recommends that the City Council authorize the City Manager to execute Amendment No. 7 to a Non-Professional Services Agreement with Rubicon Landscape Corporation to provide Citywide turf maintenance services.

 

BACKGROUND

 

On August 31, 2015, the Public Works Department issued Request for Proposals (RFP) 55027 for citywide turf maintenance and park area weed abatement. Five firms submitted proposals deemed responsive to the RFP. After review by a committee of internal staff, the five proposals were ranked and Rubicon Enterprises, Inc. (firm changed name to Rubicon Landscape Corporation as part of Amendment No. 2), a Richmond, CA-based firm, was selected based on the firm’s highest score and lowest bid price. The City entered into contract with Rubicon Enterprises, Inc. on March 1, 2016.There were six subsequent amendments to the contract to extend the term, modify services and include cost increases.

 

Annual costs for services since the start of the contract are as follows:

 

Service Contract Year                                          Total Cost

Fiscal Year 2015-2016                                          $43,736

Fiscal Year 2016-2017                                          $135,408

Fiscal Year 2017-2018                                          $130,168

Fiscal Year 2018-2019                                          $134,333

Fiscal Year 2019-2020                                          $145,721

Fiscal Year 2020-2021                                          $172,505                     

Fiscal Year 2021-2022                                          $165,062

Fiscal Year 2022-2023                                          $176,220

 

Analysis

 

If authorized, the existing contract will be extended for seven months at the monthly price of $15,859.84 for a total of $111,018.88. The new contract price reflects an 8% price increase.

 

Services provided by Rubicon Landscape Corporation include weekly mowing at all City park sites, ball field sites, and other turf locations adjacent to parks; and edging, weed abatement aeration and fertilization based on contractually established intervals. The contract will extend through January 31, 2024.

 

Staff is in the process of developing an RFP for Citywide Turf Maintenance to be issued by the end of June. The intent is to bring a new agreement to Council for approval in October. The City has the option to cancel this agreement in advance of January 31, 2024 should a new agreement be approved and executed.

 

Previous Actions

 

                     Resolution No. 2016-023 authorizing the City Manager to execute a Non-Professional Services Agreement

                     Resolution No. 2017-117 authorizing the City Manager to execute Amendment No. 1 to include three additional 1-year extensions subject to amendment

                     Resolution No. 2020-078 authorizing the City Manager to execute Amendment No. 4 and approving an additional appropriation

                     Resolution No. 2021-138 authorizing the City Manager to execute Amendment No. 5 

                     Resolution No. 2022-143 authorizing the City Manager to execute Amendment No. 6 

 

Fiscal Impacts

 

The amendment to the agreement will cost $111,018.88 for seven months of fiscal year 2023-2024. The amendment will be funded by the City Council adopted budget for fiscal year 2023-2024 in account 010-62-001-5340.

 

ATTACHMENTS

 

                     Attachment A: Resolution for Amendment No. 7 to Agreement with Rubicon Landscape Corp.

                     Attachment B: Exhibit B - Compensation Schedule FY 2023-2024

                     Attachment C1: Non-Professional Services Agreement with Rubicon landscape Corporation for Citywide turf maintenance services

                     Attachment C2: Amendment No. 1 to the Non-Professional Services Agreement

                     Attachment C3: Amendment No. 2 to the Non-Professional Services Agreement

                     Attachment C4: Amendment No. 3 to the Non-Professional Services Agreement

                     Attachment C5: Amendment No. 4 to the Non-Professional Services Agreement

                     Attachment C6: Amendment No. 5 to the Non-Professional Services Agreement

                     Attachment C7: Amendment No. 6 to the Non-Professional Services Agreement

 

PREPARED BY:  Jennifer Auletta, Deputy Director, Department of Public Works