Skip to main content
File #: 17-519    Version: 1 Name: Staff Report for Budget Amendments FY 2016-17 and 2017-18
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 9/18/2017 Final action: 9/18/2017
Enactment date: Enactment #:
Title: Staff Report for a Resolution Approving a Budget Amendment to the City's Fiscal Year (FY) 2016-17 and 2017-18 General Fund, Special Revenue Funds, Enterprise Funds, Internal Service Funds, Capital Projects Funds, and Agency Funds Budget
Related files: 17-520

Title

Staff Report for a Resolution Approving a Budget Amendment to the City’s Fiscal Year (FY) 2016-17 and 2017-18 General Fund, Special Revenue Funds, Enterprise Funds, Internal Service Funds, Capital Projects Funds, and Agency Funds Budget

 

Staffreport

SUMMARY AND RECOMMENDATIONS

 

Staff recommends that the City Council review and approve FY 2016-17 and 2017-18 Budget Amendments.

 

BACKGROUND

 

The City Council approves annual budgets based on the best revenue and expenditure information available several months prior to the actual adoption of budget appropriations. As a result, budget adjustments are periodically necessary for changes that arise and require additional budget appropriations or re-appropriations between budget line items. The City Council originally approved the FY 2016-17 Budget on June 6, 2016 and has made various adjustments since that date. The current FY 2017-18 Budget was adopted by Council on June 5, 2017.

 

DISCUSSION

 

Attachments one and two include summary and detail of budget adjustments that were made to departmental and fund appropriations over the last six months of FY 2016-17 and now require formal Council approval per Adopted Budget Policies. Attachments three and four include summary and detail of items that were included in the FY 2016-17 adopted budget that need to be carried over to 2017-18. Summaries include information regarding Funding Sources, Revenue and Expenditure Adjustments, and Net Changes in Fund Balance. Detail reports include the same information, but also provide complete descriptions regarding the purpose of the adjustments. 

 

FISCAL IMPACT

 

The projected ending fund balance for the General Fund in FY 2016-17 did not change as a result of departmental and fund appropriations over the last six months of the fiscal year. New General Fund revenues of $226,914, mainly from donations and reimbursements, funded the increase of new General Fund expenditures of $226,914.

 

The total change in the projected ending fund balance for the General Fund in FY 2017-18 amounts to a decrease of $1,050,277. This is mainly the result of carry-overs from various projects and initiatives not completed in Fiscal Year 2016-17. Should additional appropriation adjustments become necessary, they will be brought to Council for approval throughout the fiscal year as needed.

 

CONCLUSION

 

Staff recommends that the City Council review and approve FY 2016-17 and 2017-18 Budget Amendments.

 

 