File #: 19-555    Version: 1 Name: Award Main Library MCC AV Equpment (SR)
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 11/4/2019 Final action: 11/4/2019
Enactment date: Enactment #:
Title: Staff Report for a City of San Leandro City Council Resolution to Award a $670,798 Construction Contract to EIDIM Group for the Main Library and Marina Community Center Audio-Visual Equipment, Project Numbers 2016.0210 and 2016.0500; to Authorize the City Manager to Negotiate and Approve Individual Change Orders Up to 5% or $33,540 of the Original Contract Amount; to Authorize the City Manager to Negotiate and Approve Change Orders Up to a Cumulative Value of 11.2% or $75,000 of the Original Contract Amount; and to Appropriate $890,000 from the Public Education and Government Fund for the Project
Sponsors: Keith Cooke
Attachments: 1. BID SUMMARY
Related files: 19-554

Title

Staff Report for a City of San Leandro City Council Resolution to Award a $670,798 Construction Contract to EIDIM Group for the Main Library and Marina Community Center Audio-Visual Equipment, Project Numbers 2016.0210 and 2016.0500; to Authorize the City Manager to Negotiate and Approve Individual Change Orders Up to 5% or $33,540 of the Original Contract Amount; to Authorize the City Manager to Negotiate and Approve Change Orders Up to a Cumulative Value of 11.2% or $75,000 of the Original Contract Amount; and to Appropriate $890,000 from the Public Education and Government Fund for the Project

Staffreport

SUMMARY AND RECOMMENDATIONS

 

This contract provides for the complete replacement of audio visual (AV) equipment in the following public meeting rooms:  the Karp/Estudillo Room and Carnegie Lecture Hall at the Main Library, the Titan Auditorium in the Marina Community Center, and the new AV equipment in the Surlene Grant Community Meeting Room at the South Offices/Helen Lawrence Building.

 

Staff recommends the following actions:

                     Award a construction contract for the Base Bid plus Bid Alternate No. 1 to EIDIM Group (dba EIDIM AV Technology) in the amount of $670,798;

                     Authorize the City Manager to negotiate and approve individual change orders up to 5%, or $33,540, of the original contract amount;

                     Authorize the City Manager to negotiate and approve change orders up to a cumulative value not to exceed 11.2%, or $75,000, of the original contract amount; and

                     Appropriate $890,000 from the Public Education and Government (PEG) Fund for the Project.

 

BACKGROUND

 

Events held at several City public meeting rooms have been hampered by outdated audio-visual equipment, and City staff have had to improvise with the use of portable and temporary microphone equipment. This project will remove and completely replace the AV equipment in the Karp/Estudillo Room and Carnegie Lecture Hall in the Main Library and the Titan Auditorium in the Marina Community Center.  It will also install the equipment for the new Surlene Grant Community Meeting Room in the South Offices that is currently being renovated.

 

This project includes the installation of recording cameras in the Main Library and Marina Community Center public meeting rooms to allow for recording of events. These recordings can be posted on the City’s website or cable channel.  The project also includes the installation of speakers, projectors, projection screens, microphones, assisted listening devices, input panels and wall controls, sound control equipment and rack enclosures at each of the sites. This project will also replace the ceiling tile system in the Karp/Estudillo Room at the Main Library to accommodate the installation of the new AV equipment as the materials to renovate the old ceiling system are no longer available.  Additionally, the project installs cameras and necessary AV equipment to allow live broadcasting and teleconferencing in the Surlene Grant Community Meeting Room in the South Offices.

 

 

Analysis

 

One bid was received at the October 3, 2019 bid opening.  The total bid amount was $670,798 and the engineer’s pre-bid estimate was $620,000.  Staff recommends award to the lowest responsive bidder, EIDIM Group, Incorporated for the total bid amount of $670,798, which includes the Base Bid for work at the Main Library and Marina Community Center and the Bid Alternate No. 1, which includes work at the South Offices. Staff verified that the contractor has a valid license with the Contractor’s State License Board and is registered with the California Department of Industrial Relations.

 

There were no bidders with an office in San Leandro that would qualify them as a local business per the Local Inclusion Policy Ordinance.  Also, there were no bidders who met the Local Business Participation Goal by subcontracting with San Leandro businesses for 25% of the contract value. The lowest responsive bidder provided documentation that demonstrated completion of the required good faith efforts to meet the local business participation goal.  At the mandatory pre-bid meetings, staff presented the requirements of the Local Inclusion Policy Ordinance, responded to bidder questions, and provided contact information for free technical assistance if needed.  Bidders were also provided with a list of contractors performing trades applicable to the project’s construction that currently hold business licenses with the City of San Leandro.

 

As is standard in the construction industry, staff balanced site investigation costs with the risk of finding unforeseen conditions during construction as well as the design costs with the level of detail on the plans. As a result, unforeseen conditions may be encountered during construction and plan details may need to be adjusted or clarified. In order to minimize delay to the project and ensure that the scope of work is adjusted as needed to provide the highest quality project, staff requests that the City Council authorize the City Manager or his designee to negotiate and approve individual change orders up to 5% ($33,540) of the original contract amount and cumulative change orders up to 11.2% ($75,000) of the original contract amount. This will help to ensure efficient completion of the project on budget and on schedule.

 

The cable communications act of 1994 established PEG funding to improve public access to civic business.  This project has been designed to provide recordings and broadcast of civic business to the public.  The new equipment will allow meetings such as town halls, or State of the City held at each of the facilities to be recorded and shown on the City’s television channel and the internet.  Capital improvements such as this are a qualifying use of PEG funds.  Accordingly, staff recommends an appropriation of $890,000 in PEG funds for the work.  This action will minimize the use of general funds on the project.

 

Current Agency Policies

 

                     Maintain and enhance San Leandro’s infrastructure.

 

Committee Review and Actions

 

On February 1, 2017 and March 7, 2018, staff provided updates on the project to the City Council Facilities and Transportation Committee.  On May 2, 2018 the Facilities and Transportation Committee reviewed the Police Building and South Office Modification Project which included discussions on the Surlene Grant Community Room and it associated AV equipment.

 

Applicable General Plan Policies

 

Policy CSF-3.1 Library Expansion and Upgrades:

Support the expansion and upgrading of public library facilities and services to keep pace with changes in information technology and community needs.

 

Policy CSF-4.2 Information Technology:

Encourage the use of the internet, cable TV, and other forms of information and communication technology as a way to widely disburse information about City and community services, event, and resources.

 

Policy CSF-6.8 Maintenance:

Ensure that sufficient funding is provided for the ongoing maintenance of City-owned facilities, including streets, street lights, traffic signals, landscaping, street trees, storm drains, public buildings, and other infrastructure.

 

Permits and/or Variances Granted

 

Building Permits for the work were obtained from the City of San Leandro Community Development Department

 

Environmental Review

 

This project is categorically exempt from the California Environmental Quality Act  per Section 15301(c) of the guidelines.  The Notice of Exemption was filed with the Alameda County Recorder on October 2, 2015.

 

Code Compliance Review

 

The project will be inspected for code compliance by City of San Leandro Building Inspectors as part of the building permit process.

 

Summary of Public Outreach Efforts

 

The Notice to Bidders was published in the Daily Review, the South County Post, Visión Hispana and Sing Tao.  Staff also notified twenty-three builders’ exchanges and construction data firms as well as a list of contractors that asked to be notified of bidding opportunities via email. 

 

Fiscal Impacts

 

The estimated project cost is $1,047,000 as described below

 

                     Architect                     $45,000

                     AV Consultant                     $60,000

                     Construction Contract                     $670,798

                     Portable Microphone Carts                     $28,000

                     Construction Assistance by design consult                     $33,000

                     Project Management and Inspection                     $100,000

                     Project Contingency                     $110,202

                                          Total                     $1,047,000

 

 

Budget Authority

 

The AV project is funded as follows:

 

Account No.                     Source                     FY                     Amount

210-38-370                     General Fund                     FY15/16                     $50,000

210-38-374                     General Fund                     FY15/16                     $100,000

210-18-146                     General Fund                     FY16/17                     $7,000

Subtotal                                                               $157,000

 

Additional Appropriation

Account No.                     Source                     FY                     Amount

180-38-370                     PEG                     FY19/20                     $890,000

Subtotal Additional Appropriation                                          $890,000

 

Total Proposed Project Funding:                     $1,047,000

 

 

Attachment to Staff Report

                     Bid Summary

 

PREPARED BY:  Mark Goralka, Associate Engineer, Engineering and Transportation Department