File #: 24-586    Version: 1 Name: Annual Paving 21-23 Rehabilitation CCO Cap Increase
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 3/3/2025 Final action: 3/3/2025
Enactment date: Enactment #: Reso 2025-016
Title: Adopt a Resolution to Approve and Authorize the City Manager to Negotiate and Approve an Increase in the Cumulative Change Order Amount from 15% to 25% (from $532,582 to $887,637) for Annual Street Paving 21-23 Rehabilitation Phase, Project No. 2022.0050
Attachments: 1. A - DRAFT Reso Paving Da Silva Gates Project No. 2022.0050

Title

Adopt a Resolution to Approve and Authorize the City Manager to Negotiate and Approve an Increase in the Cumulative Change Order Amount from 15% to 25% (from $532,582 to $887,637) for Annual Street Paving 21-23 Rehabilitation Phase, Project No. 2022.0050

 

Staffreport

COUNCIL PRIORITY                     

                     Infrastructure

 

SUMMARY

This contract provides for the mill and overlay, and full depth reclamation (FDR) of five streets throughout the City. The increase in change order authority will be for additional base repairs and subgrade-cement mixing on Anza Way, necessitated by unforeseen poor subgrade conditions.

 

RECOMMENDATIONS

Staff recommends the following action:

                     Authorize an increase in the Cumulative Change Orders Cap from 15% to 25% (from $532,582 to $887,637) of the Construction Contract

 

BACKGROUND

On July 15, 2024, the City Council awarded a contract to DeSilva Gates Construction, LLC for $3,550,550 for the Annual Street Paving 21-23 Rehabilitation Phase, Project No. 2022.0050 and authorized the City Manager to approve individual contract change orders up to 5% and cumulative change orders up to 15% of the original contract amount.

 

This contract is for the pavement rehabilitation phase of a multi-phased project which utilized a Full Depth Reclamation (FDR) process to rehabilitate Anza Way, Beecher Street, and a short section of Dutton Avenue, in addition to the milling and overlaying of Lorraine Avenue and 139th Avenue. Previous project phases that included street sealing and curb ramp construction have already been completed.

 

Pedestrian curb ramps within the street reconstruction limits were also updated to comply with Americans with Disabilities Act (ADA) accessibility standards.

 

Analysis

 

The project is substantially complete, and the contractor is addressing punch list items. However, during the paving of Anza Way, unexpectedly poor subgrade conditions were encountered. Stabilizing the street required significantly higher quantities of hot mix asphalt (HMA) used for base repairs due to the unforeseen softness of the subgrade. Soil investigations conducted during the design phase of the project did not reveal the full extent of these poor subgrade conditions, as sampling at select points cannot guarantee a uniform representation of the entire street.

 

In addition, a higher-than-expected number of shallow utilities within the roadway required subgrade stabilization to be performed by hand, rather than with heavy equipment, to prevent damage. This labor-intensive process was far more time-consuming and costly than originally planned.

 

As a result, the total value of change orders will exceed the previously approved cumulative contract change order cap. To fully close out the project and issue final payment to the contractor, staff recommends increasing the cap from 15% to 25%, raising the limit from $532,582 to $887,637-an increase of $355,055.

 

Current Agency Policies

 

                     Maintain and enhance San Leandro’s infrastructure

 

Previous Actions

 

                     On April 18, 2022, by Resolution No. 2022-055, the City Council authorized the City Manager to execute a Consulting Services Agreement with Nichols Consulting Engineers for an Amount Not to Exceed $1,065,000 for the Design of the Annual Street Paving 2021-2023 Project, Project No. 2022.0050; to Authorize Individual Agreement Amendments Up to 10% ($106,500); and to Authorize Cumulative Agreement Amendments Up to 25% ($266,250)

 

                     On January 23, 2023, by Resolution No. 2023-006, the City Council Approved a Construction Contract with Spencon Construction in an amount of $2,471,000 for Curb Ramp Upgrades for the Annual Street Paving 21-23, Project No. 2020.0050,  and authorized the City Manager to Negotiate and Approve Individual Change Orders Up to 5% of the Original Contract Amount ($123,550) and  Cumulative Change Orders up to 25% of the Original Contract Amount ($617,750) and appropriated $465,000 for the Project in Fiscal Year 2022-2023

 

                     On June 20, 2023, by Resolution No. 2023-073, the City Council Approved a Construction Contract with Pavement Coatings Company in an amount of $9,207,613 for the Surface Seal Phase for the Annual Street Paving 21-23, Project No. 2020.0050, and authorized the City Manager to Negotiate and Approve Individual Change Orders Up to 5% of the Original Contract Amount ($460,380) and Cumulative Change Orders up to 10% of the Original Contract Amount ($920,761)

 

                     On July 15, 2024, by Resolution No. 2024-092, the City Council awarded a contract to DeSilva Gates Construction, LLC for $3,550,550 for Annual Street Paving 21-23 Rehabilitation Phase, Project No. 2022.0050 and authorized the City Manager to approve individual contract change orders up to 5% and cumulative change orders up to 15% of the original contract amount

 

 

Applicable General Plan Policies

 

                     Policy T-5.3 - Maintenance. Regularly maintain City streets and traffic control devices to ensure that streets operate safely and efficiently. The City will strive for an overall Pavement Condition Index of 76, which is the lower limit of industry best practices

                     Policy T-2.1: Complete Streets Serving All Users and Modes.  Create and maintain “complete” streets that provide safe, comfortable, and convenient travel through a comprehensive, integrated transportation network that serves all users

                     Policy T-7.2: Capital Improvements.  Identify capital improvements and other measures which improve the safety of bicyclists, pedestrians, and motor vehicles on San Leandro Streets

 

Environmental Review

 

A CEQA exemption was filed on April 14, 2022 with the Alameda County Clerk’s office.

 

Summary of Public Outreach Efforts

 

The Notice to Bidders was published in the Daily Review, the South County Post, Vision Hispana and World Journal.  Staff also notified local builders’ exchanges and construction data firms, as well as a list of contractors that asked to be notified of bidding opportunities via email. The project is described on the Engineering and Transportation Department website.

 

Two mandatory pre-bid meetings were held on May 7 and May 9, 2024, with potential bidders.

 

Prior to any construction which would affect access to private businesses or residences, the contractor provided advance notification in the form of door hangers before the work started.

 

Contract Change Order Summary

CCO No.                     Description                     Amount                                          %

1                     Increased base repair quantity, bid item 23                      $177,527.50                                                    5%

2                      Increased base repair quantity, bid item 23               $177,527.50                    5%

3                      Increased base repair quantity, bid item 23,                      $177,527.50                    5%

and speed bump installation

4                     * Increased base repair quantity, bid item 23,                      $177,527.50                                                    5%

and increased hand mix quantity, bid item 27

5                     * Increased hand mix quantity, bid item 27                       $54,292.76                                                   1.5%

 

Estimated Change Order Total                                                                                                      $764,402.76                 21.5%

 

*CCO items to be executed after City Council approval.

 

 

 

Financial Impacts

 

The estimated cost of this project is detailed below. The budget authority section has details on funding types, accounts, and authorizations. CIP accounts are carried forward for five years or until the work is complete, whichever occurs first.

 

Design and Bid                     $1,250,000

Construction Contracts:

                     Curb Ramps (Spencon Construction)                     $2,252,890

                     Pavement Surface Seal (Pavement Coatings Co.)                     $9,623,512

                     Pavement Rehabilitation (DeSilva Gates Construction, LLC)                     $3,550,550

Construction Management & Inspection                     $649,301

Construction Contingencies                     $532,583

Total Cost:                     $18,131,836

 

Budget Authority

 

The project is funded as follows:

 

                     Account No.                     Reso. Appropriation Dates & Source                     Amount

                     152-38-521                     FY 22-23 Budget, SB1 Grant                     $500,000

                     144-38-520                     FY 22-23 Budget, Measure B Grant                     $1,005,000

                     190-31-804                     FY 22-23 Budget, ARPA Grant                     $3,699,665

                     150-38-452                     FY 22-23 Budget, Cal Recycle Grant                     $165,000

                     152-38-520                     FY 22-23 Budget, Gas Tax Funds                     $965,000

                     210-38-521                     FY 22-23 Budget, General Funds                     $8,953,723

                     141-38-392                     FY 17-18 Budget, Measure BB                     $266,896

                     141-38-528                     FY  24-25 Budget, Measure BB                     $2,576,604

                     

Total Appropriation:                                                                                                                                                                                             $18,131,888

 

ATTACHMENT

 

                     A: Resolution Paving CCO Cap

 

PREPARED BY: Bennett Sanderson, Assistant Engineer, Public Works Department, Engineering Division