File #: 23-223    Version: 1 Name: Award Surface Seal for Paving 21-23 (SR and Res)
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 6/20/2023 Final action: 6/20/2023
Enactment date: Enactment #: 2023-073
Title: Adopt a Resolution to Approve and Authorize the City Manager to Award a Construction Contract to Pavement Coatings Company in the amount of $9,207,613 for the Surface Seal Phase for the Annual Street Paving 21-23, Project No. 2020.0050; to Authorize the City Manager to Negotiate and Approve Individual Change Orders Up to 5% of the Original Contract Amount ($460,380); and to Authorize the City Manager to Negotiate and Approve Cumulative Change Orders up to 10% of the Original Contract Amount ($920,761)
Sponsors: Sheila Marquises
Attachments: 1. A - Resolution Pavement Coatings Company, 2. B - Bid Summary, 3. C - Street List

Title

Adopt a Resolution to Approve and Authorize the City Manager to Award a Construction Contract to Pavement Coatings Company in the amount of $9,207,613 for the Surface Seal Phase for the Annual Street Paving 21-23, Project No. 2020.0050; to Authorize the City Manager to Negotiate and Approve Individual Change Orders Up to 5% of the Original Contract Amount ($460,380); and to Authorize the City Manager to Negotiate and Approve Cumulative Change Orders up to 10% of the Original Contract Amount ($920,761)

 

Staffreport

COUNCIL PRIORITY                     

                     Infrastructure

 

SUMMARY

This contract will provide essential maintenance on 15.5 lane miles of City roadway, with pavement surface seals applied on 90 street segments located throughout the City. 

This project will also install selected pedestrian and bike lane improvements where suitable within the paving limits.

 

RECOMMENDATIONS

 

Staff recommends the following actions:

                     Award a construction contract of the ‘base bid plus additive alternate A’ to Pavement Coatings Company in the amount of $9,207,613

                     Authorize the City Manager to negotiate and approve individual change orders up to 5% (or $460,380) of the original contract amount; and

                     Authorize the City Manager to negotiate and approve change orders up to a cumulative value not to exceed 10% (or $920,761) of the original contract amount

 

BACKGROUND

 

Streets are a critical component of the City’s infrastructure, and their condition is an important factor in the quality of life for residents and the vitality of local businesses. Good pavement conditions increase the efficiency of transporting goods, improve bicycle safety, and make walking more appealing. Each day, residents are dependent on safe, reliable local streets and roads to begin and end their daily commutes. Police, fire, and emergency medical services all rely on safe and reliable roads to respond quickly to calls for service.

Improving the City’s average Pavement Condition Index (PCI) has and continues to be a high priority for the City.  In 2014, San Leandro voters Measure HH as a guaranteed funding source for essential City services, including improvement to local roadways. In November 2014, voters in Alameda County passed Measure BB to improve local roadways as one of their main objectives. This project has a total project cost of approximately $15,127,000. Over half of the project’s funding ($8,950,000) is provided by City General Funds with the remaining amount provided by a combination of grant and gas tax funding. The City of San Leandro maintains approximately 180 centerline miles of paved roadways.  Street sealing is an annual maintenance activity that prolongs the useful life of streets, and locations included in this contract will receive either a 3/8” rubberized seal coating or thin slurry seal coat.  The treatment process is individually selected for each street based on its pavement condition.  To realize the maximum benefit from this work, streets are selected that have the lowest pavement condition index (PCI) or pavement condition yet could also still be restored using the above methods. When selecting streets, priority is also given to streets that carry more vehicles and streets that are on a bike route.

The surface seal phase of the Annual Street Paving 21-23 project will complete paving maintenance on approximately 15.5 lane miles and includes 90 street segments located city wide over 13 arterial streets, 16 collector streets, and 61 local streets. A list of the street segments proposed for treatment with this contract is attached.  This project also includes sidewalk curb ramp upgrades where necessary to meet code requirements.

In addition to the above surface seal pavement maintenance, the following pedestrian and bike lane improvements are included in this project:

                     Curb ramp radius reductions and flashing pedestrian beacons for two crossings on Estudillo Avenue at the San Jose Street and San Rafael Street intersections

                     Pedestrian bulbout and high visibility crosswalk at the intersection of Williams Street and Orchard Avenue

                     Bike lane buffer and delineators on Farallon Avenue from its current terminus east of Griffith Avenue west to Doolittle Drive

                     Class 2 bike lane along Washington Avenue from the Chapman Avenue railroad crossing north to 139th Avenue

To accelerate the project schedule, this project will be constructed in phases. In advance of this work, the City Council awarded a $2,471,000 contract to Spencon Construction in January 2023 to upgrade the adjacent curb cut ramps to comply with the Americans with Disabilities Act (ADA).  Sanitary sewer point repairs within the paving limits of this contract will also be completed under a separate contract as part of the Sanitary Sewer Point Repair project.

Analysis

 

On May 18, 2023, the City opened bids for the subject project. Two bids were received with base bids of $8,383,147 and $9,198,622, and with additive alternate A costs of $824,467 and $908,181, respectively. The pre-bid Engineer’s Estimate was $7,115,245 for the base bid, and $524,176 for the additive alternate A. Staff determined that Pavement Coatings Company is the apparent low bidder based on the base bid. Pavement Coatings Company is also the lowest bidder for the ‘base bid plus additive alternate A’ option at $9,207,613. 

 

Staff recommends the award of a construction contract to Pavement Coatings Company for the ‘base bid plus additive alternate A’ scope of work for an amount of $9,207,613.  Staff verified that Pavement Coatings Company has a valid Contractor’s State License Board license and is registered with the California Department of Industrial Relations. 

 

This project is subject to the provisions of the Community Workforce Agreement (CWA).  Each bidder was advised of the agreement in writing and verbally at the mandatory pre-bid meetings, and all bidders signed the CWA commitment form. The City’s Local Inclusion Policy Ordinance was not included in this bid because its provisions conflict with the requirements of the project’s Federal American Rescue Plan Act (ARPA) funding. 

 

As is standard in the construction industry, staff balanced site investigation costs with the risk of finding unforeseen conditions during construction, as well as the design costs with the level of detail on the plans. As a result, unforeseen conditions may be encountered during construction and plan details may need to be adjusted or clarified. To minimize delay to the project and ensure that the scope of work is adjusted as needed to provide the highest quality project, staff requests that the City Council authorize the City Manager or her designee to negotiate and approve individual change orders up to 5% ($460,380) of the original contract amount.  In addition, staff requests authority to negotiate and approve cumulative change orders up to 10% ($920,761) of the original contract amount. This contract allowance will facilitate efficient completion of the project on budget and on schedule.

 

Current Agency Policies

 

                     Maintain and enhance the City’s infrastructure

 

Previous Actions

 

                     On January 23, 2023, by Resolution No. 2023-006, the City Council Approved a Construction Contract with Spencon Construction in an amount of $2,471,000 for Curb Ramp Upgrades for the Annual Street Paving 21-23, Project No. 2020.0050,  and authorized the City Manager to Negotiate and Approve Individual Change Orders Up to 5% of the Original Contract Amount ($123,550) and  Cumulative Change Orders up to 25% of the Original Contract Amount ($617,750) and appropriated $465,000 for the Project in Fiscal Year 2022-2023.

 

                     On April 18, 2022, by Resolution No. 2022-055, the City Council Approved a Consulting Services Agreement with Nichol Consulting Engineers for the Design of the Annual Street Paving 2021-2023, Project No. 2022.0050 for an Amount Not to Exceed $1,065,000, authorized Individual Agreement Amendments Up to 10% ($106,500) and Cumulative Agreement Amendments Up to 25% ($266,250), respectively.

 

Applicable General Plan Policies

 

                     Policy T-2.1: Complete Streets Serving All Users and Modes.  Create and maintain “complete” streets that provide safe, comfortable, and convenient travel through a comprehensive, integrated transportation network that serves all users

                     Policy T-3.6 - Pedestrian Environment. Improve the walkability of all streets in San Leandro through the planning, implementing, and maintaining of pedestrian supportive infrastructure

                     Policy T-7.2: Capital Improvements.  Identify capital improvements and other measures which improve the safety of bicyclists, pedestrians, and motor vehicles on San Leandro Streets

 

Environmental Review

 

This project is Categorically Exempt per California Environmental Quality Act (CEQA) Section 15301(c) of the CEQA guidelines. A Notice of Exemption was filed with the Alameda County Recorder’s Office on April 14, 2022.

 

Summary of Public Outreach Efforts

 

The Notice to Bidders was published in the Daily Review, the South County Post, Visión Hispana and World Journal.  Staff also notified local builders’ exchanges and construction data firms, as well as a list of contractors that asked to be notified of bidding opportunities via email. The project is described on the Engineering and Transportation Department website.

 

Two mandatory pre-bid meetings were held on May 4th and 9th 2023, with potential bidders.

 

Prior to any construction which would affect access to private businesses or residences, the contractor will provide notification in the form of door hangers before the work starts.

 

Financial Impacts

 

The estimated cost of this project is detailed below. The budget authority section has details on funding types, accounts, and authorizations. CIP accounts are carried forward for five years or until the work is complete, whichever occurs first.

 

Design and Bid                     $1,350,000

Construction Contracts:

                     Curb Ramps (Spencon Construction)                     $2,471,000

                     Pavement Surface Seal (Pavement Coatings Co.)                     $9,207,613

Construction Management & Inspection                     $520,000

Construction Contingencies                     $ 1,574,760

Total Cost:                     $15,123,373

 

Funds included in the Fiscal Year 2022-2023 budget for this project are as follows:

                     Road Repair and Accountability Act of 2017 (SB1) Grant Funds in

Capital Improvement Fund Account 152-38-520                                          $   500,000

                      Alameda County Expenditure Plan (Measure B) Grant Funds in

Capital Improvement Fund Account 144-38-520                                          $1,005,000

                     American Rescue Plan Act (ARPA) Grant Funds in

Streets and Highways Fund Account 190-31-804                                          $3,699,650

                     2023 Gas Tax Funds in

Capital Improvement Fund Account 152-38-521                                          $   500,000

                     General Funds in

Capital Improvement Fund Account 210-38-521                                          $8,953,723

 

Additional appropriation of $465,000 approved by Resolution No. 2023-006 with award of curb ramp work:

 

                     Road Repair and Accountability Act of 2017 (SB1) Funds in

Capital Improvement Fund Account 152-38-520                                          $   465,000 

Total Project Funding Available:                                                                                              $15,123,373

 

ATTACHMENTS

 

                     Attachment A - Resolution

                     Attachment B - Bid Summary - Project No. 2022.0050

                     Attachment C - List of Project Streets

 

PREPARED BY: Mark Goralka, PE, Associate Engineer, Engineering and Transportation Department