Legislation Details

File #: 25-505    Version: 1 Name: Award a Consulting Services Agreement to Lee & Ro, Inc. for Design and Bid Period Services for the Davis Street Manhole Project
Type: Staff Report Status: Agenda Ready
In control: City Council
Meeting Date: 9/21/2026 Final action:
Enactment date: Enactment #:
Title: Adopt a Resolution to Approve and Authorize the City Manager to Execute a Consulting Services Agreement with Lee & Ro, Inc. in the Amount of $143,902 for Bidding and Construction Support Services in Support of Davis Street Manhole Replacement, Project No. 2018.6000; to Authorize the City Manager to Negotiate and Approve Individual Contract Amendments Up to 10% (or $14,390) of the Original Contract Amount; and to Authorize the City Manager to Negotiate and Approve Contract Amendments up to a Cumulative Value not to Exceed 25% (or $35,976) of the Original Contract Amount
Attachments: 1. A - DRAFT Resolution (Lee & Ro), 2. B - Lee & Ro CSA Scope
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.
Title
Adopt a Resolution to Approve and Authorize the City Manager to Execute a Consulting Services Agreement with Lee & Ro, Inc. in the Amount of $143,902 for Bidding and Construction Support Services in Support of Davis Street Manhole Replacement, Project No. 2018.6000; to Authorize the City Manager to Negotiate and Approve Individual Contract Amendments Up to 10% (or $14,390) of the Original Contract Amount; and to Authorize the City Manager to Negotiate and Approve Contract Amendments up to a Cumulative Value not to Exceed 25% (or $35,976) of the Original Contract Amount

Staffreport
COUNCIL PRIORITY

? Public Safety
? Infrastructure

SUMMARY

This Consulting Services Agreement (CSA) authorizes Lee & Ro, Inc. to provide design consulting services for the bidding and construction phases of the Davis Street Manhole Replacement Project, as well as additional design services that may be requested by the City. The Project will replace critical sanitary sewer manholes in Davis Street that are essential components of the City’s wastewater collection system, conveying influent flows to the City’s Wastewater Pollution Control Plant headworks for treatment prior to discharge.

RECOMMENDATIONS

Staff recommend the following actions:
? Award a Consulting Services Agreement in the Amount of $143,902 to Lee & Ro, Inc., for the subject project;
? Authorize the City Manager or her Designee to Negotiate and Approve Individual Contract Amendments Up to 10% (or $14,390) of the Original Contract Amount; and
? Authorize the City Manager or her Designee to Negotiate and Approve Cumulative Contract Amendments up to 25% (or $35,976) of the Original Contract Amount.

BACKGROUND

The Wastewater Pollution Control Plant (WPCP), located at the end of Davis Street, plays a crucial role in processing two-thirds of the total wastewater in the City of San Leandro. Sanitary sewer manholes located in Davis Street adjacent to the Plant complex convey wastewater flows to the WPCP headworks, w...