File #: 21-247    Version: 1 Name: Accept Bicycle Network West (RES)
Type: Resolution - Council Status: Passed
In control: City Council
Meeting Date: 5/17/2021 Final action: 5/17/2021
Enactment date: 5/17/2021 Enactment #: Reso 2021-074
Title: RESOLUTION of the City of San Leandro City Council to Accept the Work for the Bicycle Network West, Project No. 2014.0430 (provides for acceptance of the work performed by the Chrisp Company, filing the Notice of Completion, releasing the Performance and Payment Bonds, and releasing of Maintenance Bond upon 1-year completion of maintenance period)
Related files: 21-246

Title

RESOLUTION of the City of San Leandro City Council to Accept the Work for the Bicycle Network West, Project No. 2014.0430 (provides for acceptance of the work performed by the Chrisp Company, filing the Notice of Completion, releasing the Performance and Payment Bonds, and releasing of Maintenance Bond upon 1-year completion of maintenance period)

 

Body

WHEREAS, pursuant to a construction contract between the City of San Leandro and the Chrisp Company, approved on April 6, 2020, by Resolution No. 2020-029, the Chrisp Company completed the Bicycle Network West, Project No. 2014.0430; and

 

WHEREAS, said work was completed in accordance with the plans and specifications and to the satisfaction of the Engineering and Transportation Director, who therefore recommends that said work should be accepted.

 

NOW, THEREFORE, the City Council of the City of San Leandro does RESOLVE as follows:

 

1.                     That the work hereinbefore described is hereby accepted; and

 

2.                     That the City Clerk is hereby directed to file a Notice of Completion on said project; and

 

3.   That the bonds heretofore given for performance and payment of said

conditions are hereby discharged and exonerated from further liability

when the statute of limitations expires after the recording of the Notice of

Completion; and

 

4.                     That upon completion of the one-year maintenance period established pursuant to said contract, and to the satisfaction of the Engineering and Transportation Director, the City Manager is hereby authorized to release the maintenance bond heretofore given for maintenance of the work hereinbefore described.