Legislation Details

File #: 26-364    Version: 1 Name: Newton Construction & Management NPSA Amendment No. 1
Type: Staff Report Status: Agenda Ready
In control: City Council
Meeting Date: 9/21/2026 Final action:
Enactment date: Enactment #:
Title: Adopt a Resolution to Approve and Authorize the City Manager to Execute Amendment No. 1 to NPSA with Newton Construction & Management for Golf Course Clubhouse Exterior Improvements in the Amount of $79,153 for a Total Not-to-Exceed Contract Amount of $699,189
Attachments: 1. A - DRAFT Resolution (Newton Construction), 2. B - Newton Construction - Change Order No. 1
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.

Title
Adopt a Resolution to Approve and Authorize the City Manager to Execute Amendment No. 1 to NPSA with Newton Construction & Management for Golf Course Clubhouse Exterior Improvements in the Amount of $79,153 for a Total Not-to-Exceed Contract Amount of $699,189

Staffreport
COUNCIL PRIORITY
Quality of Life
Infrastructure

SUMMARY

On May 4, 2026, the City approved a contract with Newton Construction and Management to perform exterior improvements to the golf course clubhouse. Improvements include exterior siding replacement, new lighting, window awnings, and other enhancements. During construction, additional costs were identified related to applicable prevailing wage requirements, unanticipated dry rot repairs, and necessary electrical upgrades.

RECOMMENDATIONS

Staff recommend that the City Council approve and authorize the City Manager to execute an amendment to the non-professional services agreement with Newton Construction and Management for Monarch Bay Golf Club clubhouse exterior improvements in the amount of $79,153, for a total not-to-exceed contract amount of $699,189.

BACKGROUND

The Monarch Bay Golf Club clubhouse serves as a key revenue-generating asset within the City’s Golf Enterprise Fund, supporting food and beverage service, events, and community use.

Portions of the facility have reached the end of their useful life. The existing wood shingle siding, now nearly 40 years old, requires replacement. New lighting, window awnings, and other enhancements will improve the look of the building, enhance the dining and guest experience, and position the facility to support expanded food and beverage operations.

The project was procured using a cooperative purchasing contract using a project delivery method called Job Order Contracting (JOC). Sourcewell posted Invitation for Bids #CA-101723, for the procurement of the contract used for this project on September 12, 2023. Newton Construction and Management was a responsive bidder and entered ...