Title: Staff Report for a Resolution Awarding a Construction Contract to A Good Sign & Graphic Company for the Downtown Garage Parking Sign Project, Project No. 2013.0341
Sponsors: Uchenna Udemezue
Attachments: 1. Bid Summary - Downtown Garage Parking Sign Bid Summary.pdf
Related files: 14-201
Title
Staff Report for a Resolution Awarding a Construction Contract to A Good Sign & Graphic Company for the Downtown Garage Parking Sign Project, Project No. 2013.0341

Staffreport
SUMMARY AND RECOMMENDATIONS

The subject project will design, fabricate, and install decorative illuminated "PARK" signs near each entrance to the Downtown Parking Garage and an "ENTER" letter sign will be installed above the garage entrance at the surface parking lot. Staff recommends that the City Council award the contract to the lowest responsible bidder, A Good Sign & Graphic Co., in the amount of $43,825.00 for the subject project.

BACKGROUND

The exterior of the new Downtown Parking Garage was designed to complement and fit with adjacent downtown building architecture and not appear like a typical parking structure and as such, the construction includes only minimal signage. To increase parking usage at this location, improved and attractive signage is desired to make the facility more inviting and the entrances easy to find.

Design intent drawings that provide concept, layout and dimensions for each of the signs were prepared by SZFM Design Studios. Using the design intent, the project will include art work, detailed sign design, electrical load determinations, fabrication and installation of the signage. Staff will review and comment on artwork and design throughout the process.

Analysis

The bids were opened on April 29, 2014. Four (4) bids were received ranging from $43,825 to $120,071. A Good Sign & Graphic Co. was determined by staff to be the lowest responsible bidder. The engineer's estimate for the work was $97,000. Staff verified that the contractor has a valid license with the Contractors State License Board.

Environmental Review

Signage is a component of the garage structure; the environmental process was completed as part of the Downtown Transit Oriented Development (TOD) Strategy Environmental Impact Report (EIR).

Permits and/...

Click here for full text