File #: 15-546    Version: 1 Name: Annual Street Sealing Project Acceptance (SR)
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 10/19/2015 Final action: 10/19/2015
Enactment date: Enactment #:
Title: Staff Report for a Resolution Accepting the Work for the Annual Street Sealing Project 2014-2015, Project No. 2015.0070
Sponsors: Keith Cooke
Attachments: 1. Annual Street Sealing list
Related files: 15-547
Title
Staff Report for a Resolution Accepting the Work for the Annual Street Sealing Project 2014-2015, Project No. 2015.0070

Staffreport
SUMMARY AND RECOMMENDATIONS

Staff recommends that the City Council accept the work and authorize the City Manager to file the Notice of Completion, release the performance and payment bonds and release the maintenance bond upon successful completion of the one-year maintenance period.

BACKGROUND

Street sealing is an annual maintenance activity that can prolong the useful life of pavement. The treatments associated with this project include slurry sealing, asphalt rubber chip sealing, and micro-surfacing. These treatments involve the application of one or more layers of rock chips, crumb rubber chips produced by recycling used tires, and asphalt emulsions. The particular process is individually selected for each street based on the pavement condition.

The City was awarded a grant from CalRecycle for the use of crumb rubber chips in the rubberized chip seal process and will be reimbursed at a rate of $1.00 per square yard of roadway where that process was applied on this project. The City will be reimbursed $66,255 from the grant for this year's project.

Each year work is performed in one of our four maintenance areas. This year streets within maintenance area 4, on the west side of San Leandro, were evaluated for work. Priority was given to arterial streets and those with the lowest pavement condition index that had not deteriorated to the point that replacement was required.

Analysis

Construction is complete. A list of streets that received a street sealing treatment as part of this project is attached. The work was inspected and deemed to comply with the contract documents and City standards.

Current Agency Policies

This action is consistent with Streets and Highways Goal No. 16 of the General Plan and Action Item 16.03: Regularly maintain City streets and traffic control devices to ensur...

Click here for full text