File #: 12-350    Version: 1 Name: Annual Overlay/Rehab 10-11 ACCEPT
Type: Resolution - Council Status: Passed
In control: City Council
Meeting Date: 7/16/2012 Final action: 7/16/2012
Enactment date: 7/16/2012 Enactment #: Reso 2012-089
Title: Resolution Accepting the Work for Annual Overlay/Rehabilitation 2010-11, Project No. 10-149-38-327
Sponsors: Uchenna Udemezue
Related files: 12-349
Title
Resolution Accepting the Work for Annual Overlay/Rehabilitation 2010-11, Project No. 10-149-38-327
 
Body
      WHEREAS, pursuant to a construction contract between the City of San Leandro and Gallagher & Burk, Inc., approved on July 18, 2011, by Resolution No. 2011-147, Gallagher & Burk, Inc. has completed Annual Overlay/Rehabilitation 2010-11; and
 
      WHEREAS, said work has been completed in accordance with the plans and specifications and to the satisfaction of the Engineering and Transportation Director, who therefore recommends that said work be accepted.
 
      NOW, THEREFORE, the City Council of the City of San Leandro does RESOLVE as follows:
 
1.      That the work hereinbefore described is hereby accepted; and
 
2.      That the City Clerk is hereby directed to file a Notice of Completion on said project; and
 
3.      That the bonds heretofore given for performance and payment of said conditions are hereby discharged and exonerated from further liability; and
 
4.      That upon completion of the one-year maintenance period established pursuant to said contract, and to the satisfaction of the Engineering and Transportation Director, the City Manager is hereby authorized to release the bond heretofore given for maintenance of the work hereinbefore described.