Skip to main content
File #: 25-466    Version: 1 Name: Approve of NCE Amendment No. 6 for the Annual Street Overlay & Rehabilitation 19-21 Project
Type: Staff Report Status: Agenda Ready
In control: City Council
Meeting Date: 11/3/2025 Final action:
Enactment date: Enactment #:
Title: Adopt a Resolution to Approve and Authorize the City Manager to Execute Amendment No. 6 to the Consulting Services Agreement with Nichols Consulting Engineers for Design Services on the Annual Street Overlay and Rehabilitation 2019-2021 Project, Project No. 2020.0050, in the Amount of $154,328 for a New Total Not-to-Exceed Amount of $1,817,667
Attachments: 1. A - DRAFT Resolution Amdt #6, 2. B - Amendment #6 Scope of Services, 3. C - Original CSA between City of San Leandro and Nichols Consulting Engineers, 4. D - Amendment 1 w/ NCE, 5. E - Amendment 2 w/ NCE, 6. F - Amendment 3 w/ NCE, 7. G - Amendment 4 w/ NCE, 8. H - Amendment 5 w/ NCE
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo/Audio
No records to display.
Title
Adopt a Resolution to Approve and Authorize the City Manager to Execute Amendment No. 6 to the Consulting Services Agreement with Nichols Consulting Engineers for Design Services on the Annual Street Overlay and Rehabilitation 2019-2021 Project, Project No. 2020.0050, in the Amount of $154,328 for a New Total Not-to-Exceed Amount of $1,817,667

Staffreport
COUNCIL PRIORITY
* Public Safety
* Infrastructure

SUMMARY

This contract amendment provides for additional scope related to the continued coordination effort with Union Pacific Railroad (UPRR) and the California Public Utilities Commission (CPUC) regarding safety improvements to the existing at-grade railroad crossing near Hesperian Boulevard at Springlake Drive, coordination with the City's redevelopment efforts at Bay Fair Shopping Center, and City-requested design changes to Hesperian Boulevard. The fee associated with the additional scope is $154,328, bringing the Not-to-Exceed amount of the Agreement to $1,817,667.

RECOMMENDATIONS

Staff recommend the following:
* Approve Amendment No. 6 to an existing Consulting Services Agreement (CSA) with Nichols Consulting Engineers (NCE) that increases the contract amount by $154,328, resulting in a total contract amount of $1,817,667.

BACKGROUND

The Annual Street Overlay/Rehabilitation 2019-2021 Project includes roadway pavement rehabilitation on 15 street segments throughout the City, including arterials, collectors, and residential streets. To expedite construction, the project was split into three phases: Phase I, completed in Summer 2022; Phase II, which was completed in Summer 2025, which included the recent paving on Bancroft Avenue; and Phase III, which is anticipated to start construction in 2026 and will include Hesperian Boulevard between Bay Fair Drive and Springlake Drive.

City Council previously authorized a design contract with Nichols Consulting Engineers (NCE) for the Project. There are five (5) existing amendments to the CSA:

* Amend...