Resolution Accepting the Work for the Americans with Disabilities Act (ADA) Ramp Project 2011-12, Project No. 2012.0140
 
Body
      WHEREAS, pursuant to a contract between the City of San Leandro and AJW Construction approved on September 6, 2011 by Resolution No. 2011-155, AJW Construction has completed the ADA Ramp Project 2011-12, Project No. 2012.0140; and
 
      WHEREAS, said work has been completed in accordance with the plans and specifications and to the satisfaction of the Engineering and Transportation Director, who therefore recommends that said work be accepted.
 
      NOW, THEREFORE, the City Council of the City of San Leandro does RESOLVE as follows:
 
      1.      That the work hereinbefore described is hereby accepted.
 
      2.      That the City Clerk is hereby directed to file a Notice of Completion for said project.
 
      3.      That the bonds heretofore given for performance and payment of said conditions are hereby discharged and exonerated from further liability.
 
      4.      That upon completion of the one-year maintenance period established pursuant to said contract, and to the satisfaction of the Engineering and Transportation Director, the City Manager is hereby authorized to release the bond heretofore given for maintenance of the work hereinbefore described.