Title
Adopt a Resolution to Authorize the City Manager to Negotiate and Execute an Increase in the Cumulative Change Order Limit from 25% to 35% (from $291,338 to $407,874) for Sanitary Sewer Point Repairs 2024 - 25 and Floresta Blvd Sanitary Sewer Replacement, Project No. 2024.0120
Staffreport
COUNCIL PRIORITY
Public Safety
Infrastructure
SUMMARY
The requested increase in cumulative change order authority is necessary to address additional sanitary sewer deficiencies identified during construction that require prompt attention. The additional scope includes pipe bursting a sewer segment on Clarke Street and performing localized point repairs on sanitary sewer lines on or near Johnson Street, Fremont Avenue, Washington Avenue, and Marineview Drive. This work was urgent due to severe breaks in the lines and reports of clogs backing up sewage. Adding the work to the existing contract is the most efficient and cost-effective approach, as it avoids the delay and additional costs associated with procuring, mobilizing, and coordinating a separate contractor just for these segments. Although the remaining cumulative change order authority can partially cover the cost of the additional work, an increase of $116,536 is required to fully fund the effort. This increase would raise the contract not-to-exceed amount from $1,456,690 to $1,573,226.
RECOMMENDATIONS
Staff recommend the following action:
Authorize an increase in the Cumulative Change Orders Limit from 25% to 35% (from $291,338 to $407,874) of the original Construction Contract amount
BACKGROUND
City staff routinely inspect the condition of the sanitary sewer main lines and manholes within the City’s service area. The City’s annual Sanitary Sewer Point Repair Project addresses identified defects and deteriorated facilities that require repair or are anticipated to require repair soon. The project also includes locations that require frequent or repetitive maintenance by sewer maintenance staff and are in ...