File #: 13-257    Version: 1 Name: Walking Path at McCartney Park SR
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 6/3/2013 Final action: 6/3/2013
Enactment date: Enactment #:
Title: Staff Report for a Resolution Authorizing the City Manager to Execute an Agreement with the San Leandro Unified School District to Allow the Construction of and to Jointly Maintain a Walking Path at McCartney Park
Sponsors: Uchenna Udemezue
Related files: 13-256
Title
Staff Report for a Resolution Authorizing the City Manager to Execute an Agreement with the San Leandro Unified School District to Allow the Construction of and to Jointly Maintain a Walking Path at McCartney Park

Staffreport
SUMMARY AND RECOMMENDATIONS

The San Leandro Unified School District (SLUSD) plans to install a circular walking path from Washington Elementary School around McCartney Park for school use while school is in session and for public use at all times thereafter. Maintenance of the path will be performed by the City of San Leandro (City) with costs shared equally with SLUSD. Staff recommends the City Council approve the agreement.

BACKGROUND

The SLUSD requires the City's approval to install a circular walking path from Washington Elementary School around McCartney Park, to be used primarily for physical education purposes when school is in session. The SLUSD seeks to break ground on the project in June 2013, and is seeking City Council approval of an agreement between the City and the SLUSD for the construction, operation, use and maintenance of the pathway when it enters upon City property.

Analysis

The SLUSD will install a circular walking path from Washington Elementary School around McCartney Park. All costs to install the walking path will be paid by the SLUSD. At present, the walking path ends half way into the park. Plans include completing a circle to allow students to exercise by walking a circuitous route from the school through the park and back again. The City will maintain the path once completed, and bill the SLUSD half the costs of maintenance.

The City and the SLUSD entered into an agreement on March 21, 1960 for the construction and operation of McCartney Park. Amendments were then executed to share in the costs of maintenance for two years after the park was completed. The City has maintained the park at its cost since 1963. This action is a continuation of the cooperative relationship betw...