File #: 23-271    Version: 1 Name: Police Bldg & South Offices CCO Limits
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 6/20/2023 Final action: 6/20/2023
Enactment date: Enactment #: 2023-071
Title: Adopt a Resolution to Authorize the City Manager to Negotiate and Approve Increases in Individual and Cumulative Change Orders from 15% to 20% (from $940,200 to $1,253,600; an increase of $313,400) for the Construction Contract with D. L. Falk Construction, Inc. for the Police Building and South Offices Modifications Project, Project No. 2014.0481
Sponsors: Sheila Marquises
Attachments: 1. A - Resolution DLF change order limits increase, 2. B - DLF Change Order Summary
Title
Adopt a Resolution to Authorize the City Manager to Negotiate and Approve Increases in Individual and Cumulative Change Orders from 15% to 20% (from $940,200 to $1,253,600; an increase of $313,400) for the Construction Contract with D. L. Falk Construction, Inc. for the Police Building and South Offices Modifications Project, Project No. 2014.0481

Staffreport
Council Priority
Public Safety
Infrastructure

SUMMARY

This action will authorize an increase to the cumulative contract change order cap for the contract with D. L. Falk Construction, Inc. related to the construction for the Police Building and South Offices Modifications project.

RECOMMENDATIONS
Staff recommends authorizing an increase of the contract change order cap for the subject project from 15% to 20% (an increase of $313,400).

BACKGROUND

The subject project is for remodeling work at both the South Offices Building and the San Leandro Police Building. The construction phase has been ongoing since February 2019, and work on the final construction phase of the project is scheduled to be completed by Summer 2023.

Due to unforeseen conditions, owner requested changes, design changes, utility delays, and contractor delays, the original change order limit of 15% will be exceeded for the construction contract.

Analysis

At contract award, the project budget contained a change order contingency of 15% for the $6,268,000 construction contract. However, change orders are currently projected to total 20% of the original contract, an increase of 5% or $313,000.

Authorizing an increase in the change order cap will enable staff to complete the project without further delay. No additional funding allocation is requested at this time.

Previous Actions

* On November 7, 2016, the City Council by Resolution No. 2016-145, approved a CSA with Indigo for design services related to the Police Building and South Offices Modifications Project.
* On July 3, 2017, the City Council by Resolution No. ...