File #: 13-098    Version: 1 Name: Toyon Park Pathway Rehab - AWARD (RES)
Type: Resolution - Council Status: Passed
In control: City Council
Meeting Date: 3/18/2013 Final action: 3/18/2013
Enactment date: 3/18/2013 Enactment #: Reso 2013-039
Title: ADOPT: Resolution Awarding Construction Contract to Grade Tec, Inc. for the Toyon Park Pathway Rehabilitation Project, Project No. 2013.028 (awards a contract to the lowest responsible bidder, Grade Tec, Inc., in the amount of $47,650 from Measure WW bond funds for the reconstruction of park pathways at Toyon Park)
Sponsors: Uchenna Udemezue
Related files: 13-096
Title
ADOPT:  Resolution Awarding Construction Contract to Grade Tec, Inc. for the Toyon Park Pathway Rehabilitation Project, Project No. 2013.028 (awards a contract to the lowest responsible bidder, Grade Tec, Inc., in the amount of $47,650 from Measure WW bond funds for the reconstruction of park pathways at Toyon Park)
 
Body
      WHEREAS, the City of San Leandro did, on February 26, 2013, publicly open, examine and declare all sealed proposals or bids for doing the work described in Resolution No. 2013-017 of the City Council of said City adopted on February 4, 2013, which resolution is hereby expressly referred to for a description of said work and for all particulars relative to the proceedings under said resolution; and
 
      WHEREAS, said proposals were submitted to the Engineering and Transportation Director who has found that the proposal hereinafter mentioned is the lowest responsible bid for doing said work.
 
      NOW, THEREFORE, the City Council of the City of San Leandro does RESOLVE as follows:
 
      That said City Council hereby rejects all of said proposals or bids except that herein mentioned; hereby waives any irregularities in the proposal or bid of the lowest responsible bidder; and hereby awards the contract for doing said work to the lowest responsible bidder therefore, to wit Grade Tec, Inc., at the prices named in its bid on file in the Office of the City Clerk.
 
      BE IT FURTHER RESOLVED:
 
      That if the above named contractor is unable to execute the contract, then the City Manager is authorized to award this contract to the next lowest responsible bidder, execute all documents to effect the award, and take all actions necessary to recover any bid security from the apparent lowest responsible bidder necessary to make the City whole in its acceptance of the next lowest bid.