File #: 23-330    Version: 1 Name: Accelerated Award LCR Upslope Repair SR
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 7/17/2023 Final action: 7/17/2023
Enactment date: Enactment #: 2023-107
Title: Adopt a Resolution to Find Emergency Conditions Exist that Do Not Permit a Delay Resulting from a Competitive Solicitation for Bids and to Authorize the City Manager to Negotiate and Award an Emergency Construction Contract, to a yet to be Determined Responsible Contractor, for the Lake Chabot Road Upslope Repair Project, Project 2023.4020, and to Appropriate $450,000 from General Funds to the Subject Project
Sponsors: Sheila Marquises
Attachments: 1. A - Reso Accelerated Award
Title
Adopt a Resolution to Find Emergency Conditions Exist that Do Not Permit a Delay Resulting from a Competitive Solicitation for Bids and to Authorize the City Manager to Negotiate and Award an Emergency Construction Contract, to a yet to be Determined Responsible Contractor, for the Lake Chabot Road Upslope Repair Project, Project 2023.4020, and to Appropriate $450,000 from General Funds to the Subject Project

Staffreport
COUNCIL PRIORITY
* Infrastructure
* Sustainability & Resiliency

SUMMARY
The attached resolution will
* Find that substantial evidence exists of an emergency that will not permit a delay resulting from a competitive solicitation for bids and that the action is necessary to respond to the emergency,
* Authorize the City Manager or her designee to negotiate and award an Emergency Construction Contract for the repair of Lake Chabot Road Upslope; and
* Appropriate $450,000 from General Funds.

RECOMMENDATIONS

Staff recommends the following:
* Find that substantial evidence exists of an emergency that will not permit a delay resulting from a competitive solicitation for bids and that the action is necessary to respond to the emergency;
* Authorize the City Manager or her designee to negotiate and award an Emergency Construction Contract to a yet to be determined responsible contractor, for the Lake Chabot Road Upslope Repair Project; and
* Appropriate $450,000 from General Funds for the subject project.

BACKGROUND

The 2022-2023 winter storms caused severe erosion at two locations along Lake Chabot Road. At location 1, the upslope hillside of the road failed, depositing falling boulders and soil onto the roadway below. The eroded hillside is located immediately below two residential properties at 1700 and 1728 Astor Court. At location 2, a downslope slide eroded the hillside below the road creating a void up to the pavement edge. As a safety precaution, due to obstructing debris and the potential of additional falling rock onto the road...