File #: 12-330    Version: Name: 2009 Sanitary Sewer - ACCEPT
Type: Resolution - Council Status: Passed
In control: City Council
Meeting Date: 9/4/2012 Final action: 9/4/2012
Enactment date: 9/4/2012 Enactment #: Reso 2012-101
Title: ADOPT: Resolution Accepting the Work for the 2009 Sanitary Sewer Pipeline Replacement Project, Project No. 09-593-52-211 (provides for the acceptance of contract work by Tennyson Electric, Inc., filing of the Notice of Completion, releasing of the performance and payment bonds, and releasing of the maintenance bond upon completion of the one-year maintenance period)
Sponsors: Uchenna Udemezue
Related files: 12-329
Title
ADOPT:  Resolution Accepting the Work for the 2009 Sanitary Sewer Pipeline Replacement Project, Project No. 09-593-52-211 (provides for the acceptance of contract work by Tennyson Electric, Inc., filing of the Notice of Completion, releasing of the performance and payment bonds, and releasing of the maintenance bond upon completion of the one-year maintenance period)
 
Body
WHEREAS, pursuant to a construction contract between the City of San Leandro and D'Arcy & Harty Construction, Inc., approved on September 7, 2010, by Resolution No. 2010-112, D'Arcy & Harty Construction, Inc. completed the 2009 Sanitary Sewer Pipeline Replacement Project (Project No. 09-593-52-211); and
 
WHEREAS, said work was completed in accordance with the plans and specifications and to the satisfaction of the Engineering and Transportation Director, who therefore recommends that said work be accepted.
 
NOW, THEREFORE, the City Council of the City of San Leandro does RESOLVE as follows:
 
1.      That the work hereinbefore described is hereby accepted; and
 
2.      That the City Clerk is hereby directed to file a Notice of Completion on said project; and
 
3.      That the bonds heretofore given for performance and payment of said conditions are hereby discharged and exonerated from further liability; and
 
4.      That upon completion of the one-year maintenance period established pursuant to said contract, and to the satisfaction of the Engineering and Transportation Director, the City Manager is hereby authorized to release the bond heretofore given for maintenance of the work hereinbefore described.