File #: 11-342    Version: 2 Name: Village Marketplace
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 11/7/2011 Final action: 11/7/2011
Enactment date: Enactment #:
Title: Update on Village Marketplace Proposed Development
Sponsors: Luke Sims
Attachments: 1. Village Marketplace City Submittal Nov 2011
Title
Update on Village Marketplace Proposed Development

Body
Visioning for 1550 East 14th Street, the former Luckys/Albertsons site, began approximately five years ago when a 27-member Citizens Advisory Committee worked for two years on the City’s award-winning Transit Oriented Development Strategy which was adopted in 2007. The San Leandro Redevelopment Agency purchased the vacant site in 2009 for temporary replacement parking while the new downtown parking garage was under construction, and then for development consistent with the TOD Strategy.
The City entered into an Exclusive Negotiating Rights Agreement with Innisfree Ventures II (Innisfree) in September 2009 and has been working on plans for this site for the past two years.

Design concepts in the TOD Strategy envisioned a neighborhood retail center with a residential component on the upper floors. With the significant downturn in the real estate market over the past several years, the construction of residential units above ground-level retail businesses is not financially feasible at this time. The Village Marketplace retail component remains generally consistent with what was proposed in the TOD Strategy.

Preliminary design concepts for the Village Marketplace envision a high-quality, Mediterranean-style neighborhood retail center of roughly 28,000 square feet, anchored by a specialty grocery store. Negotiations with tenants are still in progress, however, the developer has received letters of intent from grocer Fresh & Easy Neighborhood Market, Peet’s Coffee & Tea, Chipotle and AT&T. One restaurant space and one additional retail space are also planned. The design concepts include additional retail and restaurant spaces with outdoor dining, a public plaza and gathering place, and public art.

A tentative timeline for the project follows:

Innisfree to submit Entitlement Package November 8, 2011
Negotiation of Disposition & Development Agreement (DDA) November/December 2011
Entitlements to Plan...