Title: Resolution Accepting the Work for the Airport Noise Insulation Program, Phase 2 Project No. SL-0403
Sponsors: Cynthia Battenberg
Related files: 13-129
Title
Resolution Accepting the Work for the Airport Noise Insulation Program, Phase 2 Project No. SL-0403
 
Body
WHEREAS, pursuant to a contract between the City and G.E. Chen Construction, Inc. as amended by Resolution 2011-163, dated September 19, 2011, the Airport Noise Insulation Program, Phase 2, Project No. SL-0403 has been completed; and
 
WHEREAS, Said work was completed in accordance with the plans and specifications therefore and to the satisfaction of the Chief Building Official, and he therefore recommends that said work be accepted.
 
NOW, THEREFORE, the City Council of the City of San Leandro does RESOLVE as follows:
 
1.      That the work hereinbefore described is hereby accepted.
 
2.      That the City Clerk is hereby directed to file a Notice of Completion on said project.
 
3.      That the bonds given for performance and payment of said conditions are hereby discharged upon expiration of the applicable statutes of limitation applicable thereto.