File #: 15-305    Version: 1 Name: San Leandro Ball Park Locker/Restroom Increase CO Cap (RES)
Type: Resolution - Council Status: Passed
In control: City Council
Meeting Date: 6/15/2015 Final action: 6/15/2015
Enactment date: 6/15/2015 Enactment #: Reso 2015-106
Title: RESOLUTION to Increase the Construction Contract Change Order Cap from 25% to 40% (from $60,659 to $97,054; a Change Order Cap Increase of $36,395) for the San Leandro Ball Park Locker/Restroom Refurbishment Project, Project No. 2003.0331
Sponsors: Keith Cooke
Related files: 15-304
Title
RESOLUTION to Increase the Construction Contract Change Order Cap from 25% to 40% (from $60,659 to $97,054; a Change Order Cap Increase of $36,395) for the San Leandro Ball Park Locker/Restroom Refurbishment Project, Project No. 2003.0331
 
Body
WHEREAS, the City of San Leandro did, on September 2, 2014 Award a construction contract to Southland Construction for the San Leandro Ball Park Locker/Restroom Refurbishment project; and
 
WHEREAS, the cost to complete change order work will exceed the project's Change Order cap; and
 
WHEREAS, the project budget is sufficient to accommodate the increased Change Order cost.
 
NOW, THEREFORE, the City Council of the City of San Leandro does RESOLVE as follows:
 
The project Change Order Cap is increased to 40% for the San Leandro Ball Park Locker/Restroom Refurbishment Project, Project No. 2003.0331.