File #: 20-085    Version: 1 Name: Street Overlay 2016-17 Phase 2 - SR
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 3/16/2020 Final action: 3/16/2020
Enactment date: Enactment #:
Title: Staff Report for a City of San Leandro City Council Resolution to Accept the Work of the Annual Street Overlay/Rehabilitation 2016-17 Phase 2, Project No. 2017.0050
Sponsors: Keith Cooke
Attachments: 1. Project Photos 1, 2. Project Photos 2, 3. List of work locations - Overlay Rehab 16-17 Ph2
Related files: 20-086
Title
Staff Report for a City of San Leandro City Council Resolution to Accept the Work of the Annual Street Overlay/Rehabilitation 2016-17 Phase 2, Project No. 2017.0050

Staffreport
SUMMARY AND RECOMMENDATIONS

This contract reconstructed eight (8) street segments throughout the City, including upgrades to several curb ramps to comply with Americans with Disabilities Act (ADA) requirements.

Staff recommends the following actions:
* Accept the work;
* File the Notice of Completion; and
* Authorize the City Manager to release the performance and payment bonds, and to release the maintenance bonds for the subject project upon successful completion of the one-year maintenance period.

BACKGROUND

This contract is the second contract funded by the subject project. The project was split into two phases in order to advance the construction and use available grant funds expeditiously while design work was still progressing. The first contract for repairs and reconstruction/overlay on a total of 4.2 lane miles of pavement has already been completed and accepted by the Council.

This second phase contract completed repairs, reconstruction and/or overlay on a total of 2.7 lane miles of pavement on eight segments of City streets, including upgrading 32 curb ramps within the project limits to comply with the ADA. In addition to reconstruction of streets, the project constructed two enhanced crosswalks with Rectangular Rapid Flashing Beacons on San Leandro Boulevard to support our complete streets goals and installed eleven speed cushions on several streets for neighborhood traffic calming. A list of work locations included in this contract is attached to this staff report.

The construction contracts associated with this project are an important step toward improving the City's streets, maintaining City infrastructure, providing safe access to all modes of transportation and improving the quality of life in San Leandro.

Analysis

Construction is complete and was pe...