File #: 21-066    Version: 1 Name: RES BZA 2539 Grant Ave PLN20-0001
Type: Board of Zoning Adjustments Resolution Status: Agenda Ready
In control: Planning Commission and Board of Zoning Adjustments
Meeting Date: 2/4/2021 Final action:
Enactment date: Enactment #:
Title: RESOLUTION No. 2021-001 of the Board of Zoning Adjustments of the City of San Leandro, approving Conditional Use Permit PLN20-0001 for Vehicle Storage at 2539 Grant Avenue.
Sponsors: Andrew Mogensen
Attachments: 1. Exhibit A Recommended Findings, 2. Exhibit B Recommended COA, 3. Exhibit B Recommended COAs
Related files: 14-242, 13-138, 13-141, 21-065
Title
RESOLUTION No. 2021-001 of the Board of Zoning Adjustments of the City of San Leandro, approving Conditional Use Permit PLN20-0001 for Vehicle Storage at 2539 Grant Avenue.

Body

WHEREAS, MTLG, LLC ("Applicant") submitted an application for a Conditional Use Permit for Vehicle Storage to store recreational vehicles in a parking lot at an existing facility located at 2539 Grant Avenue, zoned IG (Industrial General). (PLN20-0001) ("Project"); and

WHEREAS, 2539 Grant Avenue ("Property"), the subject site, consists of a ?12,500 square feet of industrial building, a parking lot, and an outdoor storage area on a ?204,732 square foot lot; and

WHEREAS, the Property is zoned (IG) Industrial General and has a General Plan designation of General Industrial area (IG); and

WHEREAS, a Conditional Use Permit is required to establish a vehicle storage facility at 2539 Grant Avenue. Per San Leandro Zoning Code Section 2.12.200.B.33, the applicant is required to secure approval of a Conditional Use Permit prior to establishment of a vehicle storage facility in the IG Industrial General District; and

WHEREAS, the Project is categorically exempt from the California Environmental Quality Act (CEQA) per CEQA Guidelines, Article 19, Section 15301 for Existing Facilities that involves minor alterations and negligible expansion of use; and

WHEREAS, the Board of Zoning Adjustments held a duly noticed public hearing regarding the proposed Project on February 4, 2020, at which time all interested parties had the opportunity to be heard; and

WHEREAS, the Board of Zoning Adjustments fully considered the Project application and entitlements, applicant's statements, staff report, findings of fact, conditions of approval, public comments, and all other testimony and evidence presented at the public hearing; and

WHEREAS, the Board of Zoning Adjustments finds that the staff report, Categorical...