Title
Staff Report for a City of San Leandro City Council Resolution to Accept the Work of the Annual Street Overlay/Rehabilitation 2017-18, Project No. 2018.0050

Staffreport
SUMMARY AND RECOMMENDATIONS

This contract constructed 20 street segments throughout the City, including upgrades to 86 curb ramps to comply with Americans with Disabilities Act (ADA) requirements.

Staff recommends the following actions:
* Accept the work by DeSilva Gates Construction;
* Authorize the City Manager to file the Notice of Completion;
* Authorize the City Manager to release the performance and payment bonds; and
* Authorize the City Manager to release the maintenance bonds for the subject project upon successful completion of the one-year maintenance period.

BACKGROUND

The City maintains approximately 180 centerline miles of paved roadways. Each year, the City typically conducts two pavement maintenance projects, one for street sealing and one for street overlay/rehabilitation. This contract is for the replacement of pavement (overlay) and for the repair of subgrade below pavement (rehabilitation), which addresses pavement in either poor condition and/or failed condition.

This contract completed repairs, reconstruction and/or overlay on a total of 10.73 lane miles of pavement on 20 segments of City streets, including upgrading and/or installing 86 curb ramps within the project limits to comply with the ADA. In addition, the project constructed two enhanced crosswalks with Rectangular Rapid Flashing Beacons on Farrallon Drive and School Street, respectively, and installed bicycle facilities within the project limits in support of the City's Complete Streets goals. The project also installed nine speed cushions on several streets for neighborhood traffic calming. A list of work locations included in this contract is attached to this staff report.

The completion of this project is an important step towards improving the City's streets, maintaining City infrastructure and p...